CASE STUDIES

Property: Bishop’s Fox School - New teaching block, theatre and studio

•Main Contractor: BAM Construction Ltd

•Client: BAM Construction Ltd

•Contract Value: £ 25K+

•Pipe Insulation:   1723 mtrs

•Duct Insulation:   207 sqm

•Description of Works:

The project included a teaching block with 12 classrooms and four IT suites, as well as a theatre and activity studio.

RDA provided insulation to all mechanical, heating and plumbing services from plantroom, including external plant, through distribution corridors, ceilings and risers

Despite the challenges presented by the coronavirus crisis, RDA worked closely with staff at contractor BAM to ensure the teaching block was completed in time for the start of the school year.

BISHOP FOX.png
 

Property: Nightingale Hospital Exeter

•Main Contractor: BAM Construction Ltd
•Client: T Clarke
•Contract Value: £  £300K+
•Pipe Insulation: 3000 mtrs
•Duct Insulation: 3878 sqm
•Description of Works:
The project, to transform the former retail unit on Moor Lane, involved a huge amount of work to convert the 36,000 sq ft empty space into a fully functioning hospital – complete with 120 beds.
RDA provided insulation to all mechanical, heating and plumbing  including installation of HWATT and frost protection tracer cable to services from plantroom, through external distribution routes,  including external plant areas, corridors, ceilings and risers
Despite the challenges presented by the coronavirus crisis, RDA worked closely with staff at contractor T Clarke and BAM to ensure the work was completed in time.
CUSTOMER PERSPECTIVE
Graham Kingdon, Construction Director, BAM:
“The new hospital is a fantastic facility for the South West and was a tremendous effort by the whole construction team. There was an impressive collective desire and positivity throughout to make this happen and in only 57 days.”

NIGHTINGALE.png
 

Property: Monkerton Community Energy Centre

•Main Contractor: EON
•Client: Lorne Stewart PLc
•Contract Value: £ 85K+
•Pipe Insulation: 964 mtrs
•Description of Works:
E.ON will develop a 10,000 sq ft Energy Centre and district heating network which will provide sustainable, cost-effective, low carbon source of heat and hot water to homes and businesses for the growing population of the greater Exeter area
Insulation to all mechanical, heating and plumbing  services within plant area complete with Aluzinc finish and insulation jackets
.